FG Drops Hammer: Five Major Kogi Road Contracts Axed Over Massive Failures
The Federal Government has revoked five major road construction contracts in Kogi State over what officials described as persistent delays, chronic underperformance and extensive timeline violations. According to Ireporter Online, the decision signals a renewed push by authorities to enforce accountability on contractors handling critical national road corridors.
The cancellations were confirmed on Wednesday in Abuja after a high-level contract review session chaired by the Minister of Works, Dave Umahi. Findings from the review showed alarming performance gaps on several strategic routes, most notably the Abuja–Lokoja Highway, where some contractors had delivered less than 5 percent progress despite exhausting more than 120 percent of the allotted time.
Umahi, addressing journalists after the closed-door meeting, stressed that the government could no longer tolerate such inefficiency. He noted that millions of commuters are subjected to hardship daily, insisting that contractors who fail to meet basic obligations would face decisive sanctions.
One of the terminated projects is the Culverts and Drains on the Abuja–Lokoja Road (Section 2), Contract No. 8493, handled by Sadogi Nigeria Ltd and awarded in April 2024. The work stands at 39.04 percent completion even though more than 112 percent of the scheduled time has elapsed. Umahi directed that the contract be mutually terminated, restricting the contractor to previously released funds while the ministry commences final account reconciliation.
Also affected is the Abuja–Lokoja Section 4A Rehabilitation, Contract No. 8476, undertaken by Venus Construction Nigeria Ltd. Though awarded in July 2024, the project recorded only 33.79 percent progress after utilizing over 131 percent of its contract time. The minister ordered a similar termination, allowing the contractor to operate only within the disbursed advance pending further audit.
The Abuja–Lokoja expressway — a 179km dual carriageway that serves as a major link between the nation’s capital and the South — has remained under construction for more than a decade, leading to daily traffic congestion, deteriorating pavement conditions and recurring accidents. The Section IVB of the corridor, executed by Sailthrough Engineering Services Ltd, was spared immediate termination but was given a hard completion deadline of December 20, 2025, as pledged by the company.
Another project affected is the Okene–Ajaokuta–Itobe Road Reconstruction, Contract No. 7648, supervised by CCECC Nigeria Ltd. Government records revealed that the project delivered only 2.02 percent completion despite overshooting its schedule by nearly 147 percent. Umahi ordered a mutual termination and further directed that the supervising consultancy also be disengaged for failing to meet funding and performance expectations.
Similarly, the Lokoja–Shintaku–Dekina–Ayingba Road, Contract No. 7239, awarded in February 2022 and executed by the Geld/Triacta Nigeria Ltd joint venture, was terminated after recording just 16.71 percent progress despite exceeding 125 percent of its project timeline.
The minister, however, praised JRB Construction Nigeria Ltd for steady progress on Section 1 of the Abuja–Lokoja axis and directed that the work be completed by December 10, 2025. He also applauded Trucrete Solutions Ltd for maintaining the pace of the 47.86km Koton Karfe–Abaji rehabilitation, which has reached 40 percent progress with only 58.33 percent of its timeline used.
For the dualisation of Abaji–Koton Karfe (Section III), also handled by the Geld/Triacta JV and standing at 16.71 percent completion after surpassing its approved timeline, Umahi issued a seven-day ultimatum to return to site, repair failed portions and restore smooth traffic flow, warning that further delay would attract sanctions.
The minister offered an apology to motorists for the difficult travel experience along the Abuja–Lokoja axis, assuring that the ministry is working intensively to fast-track delivery. He acknowledged President Bola Tinubu’s approval of multiple interventions on the corridor, describing it as a vital economic artery that carries heavy north–south traffic.
Umahi instructed that all outstanding works from the terminated contracts be compiled for emergency execution under a special federal works programme and urged the public to remain patient as the government accelerates reconstruction efforts.