TCN Restores Power Supply On Kontagora-Yauri 132kV Line Weeks After Sabotage
TCN Restores Power Supply On Kontagora-Yauri 132kV Line Weeks After Sabotage
The Transmission Company of Nigeria (TCN) has successfully reinstated electricity supply on the Kontagora-Yauri 132 kilovolt Single Circuit line in Niger State after weeks of disruption caused by vandalism……READ ALSO Urgent: TCN Substation Engulfed In Flames In Kano
The vandalism, which occurred on April 5, 2024, led to the collapse of towers T38, T39, and T40, resulting in blackouts in parts of Niger State and Kebbi State. However, TCN’s General Manager of Public Affairs, Ndidi Mbah, announced in an official statement on Thursday, April 18, that power had been restored to the affected powerline following reconstruction and rehabilitation work.
Mbah stated that the line was energized at 1:11 p.m. after completing rehabilitation and reconstruction work, including conductor stringing. Consequently, the Yauri 132/33kV substation is now on entire supply from the national grid.
The statement highlighted the events leading to the disruption, noting that the line tripped on earth fault relay indication on April 5, 2024. Upon patrolling the line the following day, TCN engineers discovered that towers T38, T39, and T40 had collapsed due to vandalism.
Meanwhile, during a stakeholders meeting convened by the House of Representatives Committee on Power, the Chairman of the Nigeria Electricity Regulatory Commission (NERC), Sanusi Garba, warned against reversing recent electricity tariff hikes. Garba emphasized that doing so could force the Federal government to shoulder a massive ₦3.2 trillion subsidy in 2024. He highlighted the severe financial strains plaguing the sector, including issues with foreign exchange fluctuations and non-payment for gas, which are crucial for maintaining a steady power supply.
The NERC Vice Chairman, Musiliu Oseni, supported the recent tariff increase, arguing it is necessary to prevent a total shutdown of the sector. He noted the funding shortfall in subsidies, with only N185 billion of the allocated N645 billion funded in 2023.
In response, the Chairman of the House Committee on Power, Victor Nwokolo, acknowledged the complexities of the situation and emphasized the committee’s efforts to gather input from relevant stakeholders, including the Transmission Company of Nigeria and Generation Companies.
Join our channel for more latest news https://whatsapp.com/channel/0029VaV4jB6DuMRgwqnJCF32
-
Politics2 weeks agoTinubu Makes Fresh Appointment
-
Latest News5 days agoBreaking Political Barriers: Okpebholo Names Enugu-born Igbo Leader to Edo Cabinet
-
Latest News2 weeks agoBreaking: Okpebholo Backs Words With Action As Edo Moves To Establish Special Court For Cultism And Kidnapping Cases, Writes Chief Judge
-
Politics1 week agoTinubu Makes New Ambassadorial Appointments, Seeks Senate Confirmation
-
Latest News2 days agoAPC Submits National Assembly Candidates’ Names To INEC Portal
-
Latest News1 week agoOjirami Shines at Night: Akoko-Edo Residents Hail Engr. Abubakar Momoh Over NDDC Solar Street Light Project
-
Latest News2 weeks agoBandits’ Captivity Death: Widow Rejects Illness Claims, Reveals What K!lled General Rabe
-
Politics2 weeks ago36 Governors Reveal Their Stance On State Police
-
Sports5 days agoFull List: Every Team Eliminated From The 2026 World Cup So Far
-
Politics1 week agoVIDEO: Shettima, Atiku, Masari, Governors Storm Special Prayer For Tinubu’s Late Mother
-
Latest News3 days agoAPC Dismisses Viral List Of Primary Election Winners
-
Latest News5 days agoShake-Up In Nigerian Army As COAS Redeploys Top Officers — Full List Emerges